BBMP's Koramangala-Ejipura Flyover Gets Its Own X Account as Construction Hits 60% Completion

Bengaluru: BBMP Koramangala Ejipura Under-Construction Flyover Now has a Social Media Account

The Bruhat Bengaluru Mahanagara Palike (BBMP) has launched an official X (formerly Twitter) account for the Koramangala-Ejipura flyover project, providing regular updates on one of Bengaluru's most delayed infrastructure works. The account, named 'BBMP Koramangala Ejipura Flyover Project,' shares construction progress and status reports for the flyover that has been under development for more than eight years.

The flyover is designed to be Bengaluru's second-longest, spanning approximately 2.38 to 2.5 kilometres along the 100 Feet Road corridor. It will connect Ejipura Main Road at the Inner Ring Road Junction to Kendriya Sadan Junction, providing signal-free passage through seven busy intersections and easing congestion in the Koramangala, Ejipura, and Sarjapur Road areas.

The project was originally launched in 2017 with Simplex Infrastructures as the contractor, but construction was slow, reaching only 42% completion in five years. The urban development department terminated that contract and appointed Hyderabad-based firm BSCPCL in November 2023 to take over the work.

As of July 2025, construction stands at approximately 60% completion. Of the 84 pillars planned, 70 are finished, and 437 of 762 precast segments have been installed. Ramp work is underway on the Madiwala-Ejipura and Sarjapur sides, pedestrian walkways are near completion, and asphalt laying beneath the flyover is in progress. Primary construction activities are conducted between 11 pm and 5 am to minimise traffic disruption.

The initial project cost estimate ranged from Rs. 128 crore to Rs. 204 crore. BBMP's revised deadline for full completion is March 2026, with segment installation expected to conclude by end of 2025 and final ramp and site works to follow shortly after.